Dec 9, 2018 - Dec 15, 2018: 37 projects, 522 units.

Applied 29 projects, 491 units

AddressUnitsNeighborhoodDate
10700 5th Ave NE235Maple LeafDec 13
400 Roy St125Lower Queen AnneDec 9
7709 15th Ave NW21Loyal HeightsDec 12
2436 Dexter Ave N15East Queen AnneDec 11
4214 30th Ave SW8North DelridgeDec 14
1445 S Cloverdale St8South ParkDec 10
1902 15th Ave S7North Beacon HillDec 11
9200 Roosevelt Way NE7Maple LeafDec 11
216 10th Ave E6BroadwayDec 13
7552 43rd Ave S6BrightonDec 12
2001 S Raymond St5Mid-Beacon HillDec 13
3418 23rd Ave W5Lawton ParkDec 13
623 19th Ave E5StevensDec 9
1520 NW 61st St4BallardDec 13
915 NW 52nd St4West WoodlandDec 12
202 17th Ave3MinorDec 10
9413 Roosevelt Way NE3Maple LeafDec 9
6521 36th Ave NW2Sunset HillDec 14
1908 28th Ave W2Southeast MagnoliaDec 13
3412 23rd Ave W2Lawton ParkDec 13
4329 Corliss Ave N2WallingfordDec 13
1119 N 82nd St2Green LakeDec 12
1121 N 82nd St2Green LakeDec 12
1807 E Alder St2MinorDec 12
5810 17th Ave S2Mid-Beacon HillDec 12
5908 SW Charlestown St2AlkiDec 12
8445 B Delridge Way SW2South DelridgeDec 11
13715 35th Ave NE2Cedar ParkDec 10
1914 Magnolia Blvd W2BriarcliffDec 10

Building permit issued 5 projects, 23 units

AddressUnitsNeighborhoodDate
4214 30th Ave SW8North DelridgeDec 12
7007 California Ave SW5GatewoodDec 14
9740 Lindsay Pl S5Rainier BeachDec 10
1713 Dexter Ave N3WestlakeDec 13
3220 Alki Ave SW2AlkiDec 14

Completed 3 projects, 8 units

AddressUnitsNeighborhoodDate
5544 15th Ave S4Mid-Beacon HillDec 12
4601 S Director St2DunlapDec 14
5546 A 15th Ave S2Mid-Beacon HillDec 12